Updating Tasks by Batch
Projects > All Projects > (selected project) > Tasks > Batch Actions
Batch Actions enables you to update several tasks at once. A two step wizard prompts you to:
- Select tasks.
- Select an action.
Running Batch Actions
- Select the Projects > All Projects page.
- Click an existing project.
- Select the Tasks tab.
- Click Batch Actions.
- Select tasks on the Choose Tasks tab.
- Select one of the following actions to perform on the Choose Action tab.
- Slide Tasks - Slide dates forward or backward by a specific number of days or months for selected tasks.
- Slide -
Forward
or Backward
- Slide Dates -
Start Dates
, End Dates
, Start
& End Dates
- Duration -
<N>
<periods>
- Assign Members - Assign selected users to selected tasks.
- Remove Members - Remove selected users from selected tasks.
- Delete Tasks - Delete selected tasks and their related data.
- Update Status - Update the status of selected tasks.
- New Status - Select as status.
- Update Percentage - Update percentage of selected tasks.
- New Percentage - Select as status.
- Click Finish.
- Click Save to save the project.